Judy Stokley and Terry Little Lead Acquisition Reform Pamela Bowers, Managing Editor
AMRAAM, JASSM program directors dramatically cut costs, increase performance.
Two Air Force missile programs are bringing in a
new era of acquisition reform that is providing the
United States and allied war fighters with better and
lower cost weapons. The heart of these programs is a
more commercial business arrangement with the government
and a single prime contractor in each case.
The first is the Advanced Medium Range Air-to-Air
Missile (AMRAAM) program. It will yield an estimated
life-cycle cost savings of more than $590 million
from streamlined business practices, and optimized and
significantly reduced government and contractor manpower,
according to Judy A. Stokley, member of the
Senior Executive Service, director of the Air-to-Air
Joint Systems Program Office (SPO) Air Armament
Center at Eglin Air Force Base in Florida.
 AIM-120 advanced air to air missile
Prior to 1997, AMRAAM was a "Super SPO" manned with 325 government and support contractor people. Business was
conducted the traditional way with intensive oversight of two competing contractors producing AMRAAM missiles and associated
support equipment. Then in 1998 a buyout resulted in a single prime contractor, Raytheon in Boston, Mass., accepting Total System
Performance Responsibilities (TSPR) with the government defining its enabling roles.
Another pioneer in the Department of Defense's (DoD) acquisition reform and streamlining efforts is Terry Little, program manager
for the Joint Air-to-Surface Standoff Missile (JASSM) program. Little has incorporated numerous reforms in the JASSM development effort,
and with its prime contractor, Lockheed Martin Missiles and Fire Control, Orlando, Fla., is dramatically reducing cost and acquisition
schedules. He says current projections peg the unit cost of the missile near $300,000, compared with an original threshold cost of $700,000,
and $1.6 million for its predecessor, the Tri-Service Standoff Attack Missile (TSSAM).
Little notes that the government will save more than $960 million (in 1995 dollars) in fixed costs over JASSM's production period.
This is possible he says, because instead of mandating countless military specifications, the JASSM program has just three key performance
parameters: range, missile mission effectiveness, and carrier operability. All other requirements are tradable to keep costs down, he says.
Both government programs also boast of acquiring a bumper-to-bumper lifetime repair warranty on the missiles.
To understand more completely the acquisition reform measures Stokley and Little have initiated,
CrossTalk
recently interviewed
these two pioneers at Eglin Air Force Base. Following is a condensed version of their comments. For full comments see
www.stsc.hill.af.mil
CrossTalk:
How has acquisition reform shaped the acquisition
strategy on your program? What impact has it had on product
cost, schedule, and performance?
Stokley: When AMRAMM was established in the late 1970s,
we brought on two competitive producers, then Hughes in
Tucson, Ariz. and Raytheon in Boston, Mass. At the time we
were in the cold war, and we planned a procurement strategy that
was based on the Air Force and Navy buying 24,000 missiles in
10 years. When I came back to the program in 1997, the plan
was then for them to buy a little over 10,000 missiles in 21 years.
So the acquisition strategy needed to change completely because
we had two full-up producers and factories, the government controlled
all of the more than 370 specifications, and we mandated
a build-to-print package to each of those contractors. They were
in head-to-head price competition each year to build the missiles.
We began to discuss with the two contractors how to split
the work to increase efficiency. Coincidentally, Raytheon decided
to buy Hughes. When they did that, we had the real opportunity
to set up a team business structure and partnership, and a long-term
pricing agreement with Raytheon. Once one producer was
responsible for the product, we were able to divest a lot of the
cross checking and government control, and allow Raytheon to
assume total system performance responsibility (TSPR).
We wanted to save significant dollars out of every unit's
procurement cost... and simultaneously shift more of our
appropriated dollars to buying missiles as opposed to buying
overhead. And we wanted to significantly reduce the size of the
government workforce required to execute the program.
In a year and a half we accomplished those three initial goals,
and established a business framework that would last for the life-cycle
of the program. We wanted to save 25 percent of average
unit cost. We actually saved 30 percent. Then we rolled some of
that back into investments, one of which was software modernization.
We were also able to reduce our workforce by two-thirds.
Little: It [JASSM] has shaped the entire acquisition reform program.
We have found it necessary to use entirely different than
normal processes in order to achieve our goals. First of all we
picked contractors based on past performance. In our case, past
performance was equal to price and missile performance combined.
We did not ask the contractor to provide us any description
of his processes. We merely looked at his performance on
recent relevant activities that were similar to ours in those
specific areas that we felt were important to our program.
Next, we essentially redefined the government's role: to
establish the requirements, select the contractor, and work interfaces
that are outside of the contractor's control. There is no
function that we have assumed for oversight, other than what I
exercise and the procurement contracting officer. Their [government
employees] responsibility is to make the contractor successful
as a player.
The other thing we did is we have no processes required in
our contract. It is strictly a performance specification. So we do
not care how they do what they do, as long as they meet the
performance requirements.
The end result is we are right now projecting it will be
under the objective of $400,000 per unit. Our schedule is going
to be about seven years, which is about 60 percent of what it
has taken historically to do this, and the performance is equal to
and some respects better than the predecessor program.
CrossTalk:
What impact have the changes had on the way
your software acquisition organization does business?
Stokley: We simultaneously looked at this program in two ways:
the near-term problem, which was having two vendors, and too
much infrastructure cost. We also wanted to set up the program
for long-term performance gains for war fighters. One of the
things we decided needed to be done was to modernize the
processors used in the missile and to modernize its software.
The software was still in Hughes-specific assembly code, and
the processors were Hughes-specific. Long term we felt it was
important to move to a commercial processor so that there
would be common processor architectures and people who could
work with those architectures across the site. We received
approval to reprogram part of our savings back into the program
to convert to a Motorola 750. Raytheon is converting part [not
all] of the software to C++ that has to be changed when we
upgrade the system for electronic countermeasures.
The cost to upgrade the AMRAAM processor and re-host
the current software in a commercial high order language is $20
million with a projected payback of $62 million dollars. This
payback comes from two sources: lower Preplanned Product
Improvement (P3I) phase 3 costs ($12 million), and lower software
development costs ($50 million) achieved over the 15-year
life cycle of the missile.
Little: Our contractor has TSPR. We have a warranty. Our role
is to do the things the contractor cannot do, or that we can do
better. Essentially it is [our job] to help him succeed.
In general, what the government engineer brings to the
table is a broader experience than what your typical contractor
has. In our case, it may come from working on other weapons
systems programs where there are some lessons learned. In the
case of JASSM, we have some people who worked on its predecessor
program Tri-Service Standoff Attack Missile. In the software
area, the processes and lessons learned are pretty codified.
The government does not particularly have anything to add,
and I have no dedicated software people in my organization.
That seems to be working since Lockheed is doing quite well
in the software area.
CrossTalk:
Describe the business arrangement between
government and contractor. How are various platform
interfaces managed?
Stokley: First of all both [original] contractors already gave the
government a 10 year bumper-to-bumper warranty. In key business
shifts, we got away from annual pricing and established a
long-term pricing agreement with Raytheon.
Now, what did the contractor get? We gave him control of
the hardware below the missile performance specification.
Previously the government controlled some 370 specifications
that required a fairly lengthy government review approval cycle
to change. He [contractor] is now free to make those decisions
as long as he meets performance, continues to give us this warranty,
and gives us the product at this price. The contractor can
build off common hardware or common vendors with other
products, which allows him to get some economic buys.
A second thing we gave him is self-oversight. He does his
own verification testing and signs a compliance form when he
sells the product to us. We do not have government quality
inspectors on the floor. He does his own quality inspections and
uses his own processes to ensure the quality of the product.
Lastly, we have a full and open partnership. We work with
him to look at his books and financial health. We try to ensure
we make smart business decisions together so he stays healthy.
He looks at our government financial reporting, obligations, and
expenditures to ensure that we keep our [contractor's] billing up
and do not lose money. We formed an international business
team with him so Raytheon gets to be part of our government
team working with international companies to sell missiles.
Little: We have a contract, of course, but the contract does not
define the relationship. It is kind of a constitution or a charter.
The details of the relationship are defined by how you behave
day to day. It is a very, very close team relationship characterized
by collaboration, trust, full openness, quick illumination of disruptive
influences, and open transmission of information. There
is nothing I know, or that I think I know, or suspect that
Lockheed does not know. That kind of open, honest communication
has gone a long way in helping us work through problems
that inevitably occur in any development program.
One of the things I have done with the government team is
I have tried to destroy individuals' focus on their functional
stovepipe. For example, it is unacceptable to me for a contracts
person to say, 'The contract is my problem and as long as the
contract's all right, I have done my job.' That is not the way
teams operate. The team must operate to an overall goal-a goal
that in our case includes schedule, system performance, life
cycle costs, profit for Lockheed and its suppliers, as well as
being a pioneering acquisition reform program.
Regarding interfaces, I have an entire integration team.
Essentially it is one person per aircraft whose job it is to work the
interface between that aircraft and our missile. Lockheed has a
parallel arrangement with the aircraft and subcontractor. In the
end the team produces an interface control document that everyone
signs and adheres to.
CrossTalk:
What other ways has acquisition reform enabled a
reduction in the cost per product?
Stokley: There were three areas that allowed us to save a very
large number of government work force. One, we eliminated
cross checking and duplication where we used to do independent
analyses to check the contractor. We got rid of all official
data managers and all official configuration control managers.
Because we do not control those 370 specs, we do not have all
the data and reports. Instead, the contractor does this, and
always had to anyway. If they are at the plant, my enablers will
sit in on his configuration control boards as a part of his work
activities. My folks are not there to check the contractor. They
are there as co-workers and facilitators.
Little: The first [JASSM] systems off the production lines will
be under $400,000-unlike the old theory that if we produce
enough of these, costs will finally go down. Our results are not
only due to up-front planning but also up-front effort. During
the program's preliminary design and risk reduction phase we
spent as much time and more money on manufacturing risk
reduction as we did on performance risk reduction. Second is
price-based acquisition. The contractor offered us a very attractive
price for the first five production lots. He has the ability to
make any change that he wants at any time without the government's
OK-so long as it does not affect performance. He has
the right to put in something that may lower his cost to produce
the missile, but he must pay for it. We have no provisions
for value engineering change proposals.
Furthermore ... when we decide to negotiate a fair and reasonable
price for additional lots, we are not going to look at
what his costs are. We are going to look at how his price compares
to the price for similar missiles in the world marketplace.
As long as we get a price equal to or better than similar missiles,
we are happy.
CrossTalk:
Do you feel there is a business case for Software
Process Improvement?
Stokley: Not as a stand-alone item. First of all we do not buy
software. We buy a well nurtured missile system that has software
in it and includes: support equipment in the field, analyses
of flight tests that fold back into production and repair lines, a
warranty, and high reliability. So I think of buying a missile system.
I do not think of buying software or hardware.
I think of process improvement more as an attitude that we
motivate industry to take to keep this a healthy viable product
that meets its requirements and is affordable. I have great worry
and trepidation about singling out any one element of a program
and doing process improvement on it. I think the parts of the
program are so interdependent that it is easy to optimize one
thing at the expense of something else, often unintentionally.
Little: No, I am concerned with product, not processes. I am
also no fan of government or third party process or capability
evaluation as a way of predicting future performance. During
the JASSM source selection we evaluated the offerers' past performance
in software development as we did on my previous
program, the Joint Direct Attack Munition. In both cases
Lockheed got very good grades from their customers on the
timeliness and quality of their software developments. They also
performed admirably in the work we gave them. I think, in retrospect,
that their great performance was due to superb execution
of processes that were only moderately mature. I have no
problem with that. We have no software processes required in
our contract. Lockheed has to meet a performance specification
and a schedule; I do not care how they do it.
CrossTalk:
What are the most significant lessons that have
been learned under acquisition reform?
Stokley: Historically what the government has always measured
for contractors who are doing the repair work is turn time. How
long does it take the contractor to repair each unit? When we
asked the contractor, given that we want 90 percent or better
availability of all the missiles we bought worldwide, 'how can we
get there?,' he said, 'Well, quit measuring turn time-grade me
on availability. Let me decide how I run these units through the
repair line.' So if 90 percent of them can go out in three days,
and they need two months on one of them, we do not penalize
them for the one that needs longer. It also allows them to take
over sparing. So we changed contracts to manage availability and
have been at 92 percent to 95 percent availability since.
Second... getting a certified price package normally takes
about three to six months. We knew we needed to get the contract
awarded on time, so we actually briefed the auditors and
asked them to come do this in parallel with us. Instead of the
contractor preparing the package and handing it over to government,
everybody went and lived at Raytheon. We turned around
the whole thing in 30 days and awarded the contract on schedule.
It was the first big thing the team did together. It really
showed them that they could overcome barriers, and the people
bonded quite well during that.
Third... the program had suffered a budget cut in
development; it was considerably behind in expenditures. So I went to
my counterpart at Raytheon and told him it [budget cut] was
because he was behind in his expenditures. He said he never
knew what those were used for. After all those years of working
with the government, our AMRAAM team did not know how
the Planning Programming and Budgeting System (PPBS)
works. So I asked my financial manager to prepare a PPBS tutorial
and go out and brief the company [Raytheon] at all levels.
Since then we have been green in every appropriation from 1998
through 2000. It is the first time in AMRAAM's history that we
have not lost a single dollar to budget cuts.
Little: When I came on to the program... we had essentially
done no preparations for milestones; the mandate was to award a
contract in seven months. The team at the time said there was no
way to do that in under a year. I told my folks we have one objective,
and that is to award a contract in seven months, or we are all
out of it. About three hours later people returned and said there
was no way it could be done. I told them [on Tuesday] that on
Friday, I wanted them to tell me what they were going to do-
and they did. They said they were not going to do the traditional
process. They wanted to do oral proposals, use past performance
instead of lengthy process descriptions, and focus on things really
important to the program. We did it and awarded a contract in
six months. A lot of the things in acquisition reform will come
when people perceive there is urgency.
Second, when we utilized past performance, a lot of people
argued that we would have a protest; that it would be too subjective.
In fact, we did have a protest, and it was a lot of work. It
went to the General Accounting Office, but it was not sustained.
CrossTalk:
Is there room for further acquisition improvement?
Stokley: Yes. Historically we have acquired a very large amount
of government-furnished equipment over the two plus decades of
the program. We are trying to whittle away at that and decide if
we still need it, because some of it is very old. And of course
someone is tracking it and paying for storing it somewhere.
Second, for government-furnished equipment that is still
useful to the program, how do we streamline its management
and accountabilities? We would like to transfer as much of it as
possible to Raytheon's control since most of it is used in their
testing and analysis processes.
Third we are still interested in doing price-based vs. cost-based
procurement when we let our next long-term pricing agreement
for 2002 through 2007 buys. We are exploring opportunities
to use the war fighters' price requirement as documented in
the Operational Requirements Document, as well as our factory-price
model and our data from our cost as an independent variable
exercise on Phase 3 P3I to justify price-based procurement.
We would still like to see a lot of streamlining in the international
sales market and more use of direct commercial sales. I
have a foreign military sales office here ... I contract with
Raytheon on behalf of the [foreign] countries. One of my rules of
life is "very seldom is the middle man a good thing," because
every place you send money through, they will get some small
share. But thus far Raytheon has not been allowed to conduct
direct sales to many foreign countries.
Lastly, I would really like to see expansion of real acquisition
reform across all services and all programs. It is very difficult
for our industry to really grow and prosper as a result of
acquisition reform if it is not implemented across a plant site.
Little: First, more widespread use of price-based acquisition.
Second, more use of past performance in lieu of process descriptions.
I know companies typically use proposal writers who
know all the buzz words to put in a proposal about software
processes, but these words say nothing about the company's
ability to actually do software development or control software
schedule. Past performance, while not perfect, is the best indicator
we have for future performance. Third, we need to break
down the barriers that preclude predominantly commercial
companies from doing defense software.
The biggest problem we have in software is not a software
process maturity process; it is the ability of the predominant
defense companies to find or retain highly qualified software
engineering people. As a solution to this problem, I would like to
see our defense prime contractors look at subcontracting some or
all of their software development to commercial companies with a
proven track record like Computer Associates, Microsoft, or
Oracle. Right now this would be difficult because we have barriers
that would preclude defense contractors from going to commercial
companies for development-barriers like cost accounting
systems and others associated with the way we do business.
Judy A. Stokley is the program director of the Air-to-Air Joint
Systems Program Office, Air Armament Center (Air Force Materiel
Command), Eglin Air Force Base, Fla. She leads a large extended
team of civilian and military personnel, as well as several major
defense companies, in delivery of critical systems to the warfighters.
Stokley began her Air Force career in 1979 as a mathematician in
the Armament Laboratory and, subsequently, worked in development
planning and system program offices. She has a bachelor's
(University of Alabama) and a master's (University of West Florida)
degree in mathematics. In 1991 she graduated from the Defense
Systems Management College at Fort Belvoir, Va., and in 1993 was
approved for membership in the Air Force Acquisition Corps. In
1999 she was promoted into the Senior Executive Service.
Terry R. Little has been the program director for the Joint
Air-to-Surface Standoff Missile Joint Program Office since 1996 and
has more than 15 years of experience as a system program director
for major programs. Previously he was the program director for
the Joint Direct Attack Munition Program Office. Little entered
the Air Force in 1967 and was a distinguished graduate of
Officers Training School. Before becoming a civilian employee in
1975, he served on active duty as an aircraft maintenance officer,
a computer systems design engineer, and an acquisition program
manager. As a civilian employee he has been an operations
research analyst, a program director for a classified project, a
deputy program director and a weapons development planning
manager. Little has a bachelor's degree in mathematics (University
of Texas), a bachelor's degree in English (Southern Methodist
University), a master's degree in systems analysis (Air Force
Institute of Technology School of Engineering), and a master's
degree in business administration (University of West Florida). Additional Comments from the Stokley/Little Interview
During her interview with CrossTalk, Judy Stokley, AMRAAM
director, also addressed the following questions.
CrossTalk:
What were your three main goals of Vision 2000?
How successful were they?
Stokley: We wanted to save significant dollars from every procurement
cost. At the time, we had a lot of infrastructure cost in
the program so the unit cost was quite high. This was because the
quantities had decreased significantly, as had happened with all
systems after the fall of the Berlin wall, and the Department of
Defense budget changed. We wanted to drop that [cost] down
and, second, simultaneously shift more of our appropriated dollars
to buying missiles as opposed to buying overhead. Third, we
wanted to significantly reduce the size of the government workforce
as required to execute the program. In about a year and
a half we accomplished those three initial goals. We also tried to
establish a business framework that would last for the lifecycle of
the program. We wanted to save 25 percent of average unit cost.
We actually saved 30 percent. Then we rolled some of that back
into some investments, one of which was in the software area.
And within one year we were also able to reduce our workforce
by two-thirds. So we met our initial goals very quickly, and set up
this long-term business strategy that is working quite well.
CrossTalk:
How do you check contractor quality, or is it a complete
trust relationship?
Stokley: It's both. First of all we use the insight of government
engineers who live with the contractor working with his engineering
force who are doing the design and upgrade work. The second
way we track quality is through testing. There are more than
100 AMRAAMS fired each year by various test agencies, primarily
field operators who shoot the missile down with what is called
the Weapons System Evaluation Program at Tindle. As far as
quality in manufacturing on the floor, although we're out there
with the contractor all the time, we don't do any government
cross-checking of his product.
CrossTalk:
Do you see contractors using more off-the-shelf software?
Stokley: I think he does it, but I don't think he invests a lot of his
own money to go out and search for commercial applications.
The one thing, since our system undergoes such significant environmental
challenges on airplanes, including vibrations, acoustics,
heat, and cold, it requires a significant search for a lot of change
to commercial parts. So unless it just turns out that there is something
that comes along, I don't think that there's a big shift. After
all, we're not in original development where you go out searching
for the parts, we already have them along with established vendors.
CrossTalk:
How do you determine what the contractor's financial
health should be?
Stokley: That's a bigger picture question. How did we come up
with all these things to do under the Vision 2000 business structure
so there is benefit to the contractor and benefit to us? There
are four tenants in Vision 2000. First, it is a win-win business
strategy. We look at things and acknowledge what is the right
thing to do. Then, how do we make it work for both the government
and the contractor. The third tenant is teamwork and trust.
Fourth is that the contractor has full system performance responsibility.
He has control of capability for his product.
Now how did we come up with all this vision and business
structure that make this thing work together? It is really quite
interdependent, and yet part of the puzzle. We realized that when
we began analyzing the program in 1996 that cost had gotten out
of control. We had way too many government people and were
not getting enough product. Then when Raytheon purchased
Hughs, we went through a somewhat traditional approach to
identifying as a team with Raytheon our vision, our objectives,
and what would enable us to achieve these objectives. Things like
self oversight and open financial books came out in this environment.
Raytheon trusted us enough to explain how they are graded
within their corporation regarding profit margins. I opened up
to them what my budget process is and what briefings I take to
congressional staffers. So we really opened up our worlds to each
other. We defined how we would reach this Vision 2000.
We have continued our off-sights together, using one facilitator
now for three years. We do two off-sights a year. One is to
establish that year's specific goals and objectives. A second evaluates
where we are that year and identifies any problems or barriers,
and also identify places to improve next year when we set our
goals. It is a continual ongoing process that requires quite a bit of
nurturing. You don't just set a business relationship, walk away
and let it execute itself. It is not static. We're always working
together identifying how to make this work better and what has
changed in our environment.
For example, when we established Vision 2000 we were only
authorized to sell the AIM-120 B missiles to our international
customers. A big change this year is that we were approved to sell
the AIM-120 C a later block configuration. So that changes the
business mix of our unit. Now we want to go out and visit all
these countries and offer them the missiles. So one of the thing
we did this year was form a new international team to go out and
brief 19 countries around the world on this new missile product.
CrossTalk:
Did these additional international sales contribute to
decreasing per copy cost of AMRAAM along with the other
measures you mentioned earlier?
Stokley: The way we did that is our savings were calculated on a
base FMS quantity. As you know, FMS quantities can be quite
volatile year to year. We set a pricing model around that so we're
able to price the product plus or minus certain quantities.
Depending on how many we sell we get a better price or more
expensive price. We were quite fortunate since we had very good
pricing model for changes in quantity based on historical data.
We sized the program on U.S. production then modified costs up
or down as our FMS goes up or down.
CrossTalk:
Did the maintenance concept and warranty cut back
significantly on deliverables that you typically see in a government
contract such as software test reports and thus contribute to the
savings?
Stokley: The contractor had always been the repair agency for the
missile. We never had an organic depot. And we have had the
10-year warranty for a number of years. We did do some streamlining
in sustainment, but I don't want you to think that's the only
reason we have all those no CETRALS (?) We have almost no
data items on this product. We don't get any reports, other than a
safety report. We have an electronic data repository that both the
contractor and we can access, which we use for all reporting and
monitoring processes.
CrossTalk:
Is the jury still out on ACT reform? As systems get
into maintenance and sustainment phase, do we know that it will
be successful?
Stokley: We used JDAM very successfully in Kosovo, which had
been developed following acquisition reform business practices.
So I think we have seen in a few cases that you can certainly
deliver a good product that works under this regime. We haven't
had any of those business practices in place for 20 years, so we
can't certainly say they are proven for that time. My own view is
that what we know about human nature in business motivations
is that the less you fragment work and clearly identify who is
accountable in name and cost, then the better results you'll get.
When we get companies under ACT reform to truly be
accountable for long-term price and warranty, it is difficult for me
to see how that can be less than a good thing. I think it is much
better than the way we used to do business, which was to fragment
the work so much that it was hard to determine who was
accountable for the end product. I think you'll see things improve
in the areas where we have fully implemented it.
CrossTalk:
Does a higher level of process maturity allow the contractor
to provide a better product and instill confidence?
Stokley: In my experience I have managed several major activities
that were very software intensive. I think you're talking about the
Software Engineering Institute's (SEI) levels of certification. And
I've been through all that process. I believe that the SEI level certification
is a very poor measurement of how well they [contractors]
perform. It's an exercise that makes everybody feel good. But
I've not seen that it is very indicative of how different teams within
the company really work.
You can go into a company that is certified at Level 3, and on
your particular program they can have a terrible situation for software
development. And you can walk across the hall to another
program that will be on track with very good metrics, structure
and flow-down requirements, verification processes, and be writing
test cases ahead of time. Why? The company is Level 3; the
same functional office approves both groups.
So I think this certification thing is at best some really aggregate
level indicator. But I would never rely on it as an indicator of
how my team is going to perform. What's important to me is not
what level the company has achieved, but how my team's performing.
What I look for is a good flow down of requirements, a
good structure to identify the work and that it is being accomplished,
and a clear verification process to determine that the
work is correct. I wouldn't choose or turn down a contractor
based on whether he was Level 2, Level 3 or Sigma 6.
CrossTalk:
How do you choose a contractor to open your entire
books and life to knowing it will work?
Stokley: I have worked with basically every major company in
this country: Boeing, Lockheed, Martin Marietta, Raytheon, and
numerous small companies including Marvin, Alliance,
Chamberlain. So far I have not ever been treated unfairly or
unethically. And I've never felt that I was treated in any way dishonestly.
I always go in believing that companies are in the
defense business to make a profit; and also, because they have
some views about patriotism and doing what's right for our country.
So far I have not been disappointed. I have always gone into
my work with other government agencies and industry believing
that if I'm honest and straightforward with them, they will be
with me. And whatever happens, I'll get better results than if I
had tried the opposite approach. If someone isn't going to work
well with you they're sure not going to work better because you're
hiding your motivations and your data.
That isn't to say it's trouble free, that me and my counterparts
don't debate sometimes. Debate is healthy. Sometimes I have to
give, and sometimes they have to give. Chuck Anderson is my
counterpart at Raytheon now. He and I communicate this to our
team by saying debate is OK, disagreement's OK. We want to
talk about it and figure out the right approach. We always ask
first, 'What is the right thing to do for the war fighters and the
tax payers?' Once we define that, we'll get to who's going to pay
for it.
The very last thing we ever do is figure out if it's under a contract
somewhere. I never look at my contracts, and I don't expect
my industry partner to be off reading his. We should be deciding
what's the right thing to do, and who can afford to pay for it.
We'll pool our resources however necessary to get the right thing.
If we can't do the right thing for the war fighter and tax payer,
and it's just way too expensive in this case, then we're going to
put our story together, go up the system, and say, 'Here's some
things we can do and some things we can't do.' So far that's
worked. So I just don't have that fear. And it troubles me that so
many people seem to have this fear.
CrossTalk:
How do you use your government people?
Stokley: Government people handle several really important
things that I don't think we can expect industry to take on. One
is working with combat pilots to establish their operational
requirements. Then they translating those into missile performance
specifications. We serve as the bridge between industry and
our war fighters. The government technicians have to get enough
understanding from the contractor to know what's possible with
technology. Then obtain enough understanding of the war fighter's
capability to build this bridge that flows from requirements to
specifications.
Their second job ... is we facilitate and manage the interfaces
with a variety of government agencies, one being aircraft program
offices and aircraft contractors. We try as much as possible to get
major fighter manufacturers to work together on interface management.
Remember the weapon and the two airplanes have different
budget line items. So we're constantly trying to ensure that
with our different budgets and requirements the weapons are
going to be properly integrated and fielded so they work properly
when they hit the field together.
Third we handle a lot of field activities including safety for
field, product and test ranges, and environmental requirements at
different bases where the missile is stored and used including
other countries. Interface management that requires a technical
knowledge on both sides is a lot of what my folks work on.
Lastly, since we do launch a large number of missiles
annually-well over 100-a lot of coordination is required to get all the
data from those missile shots to Raytheon. There are classification
issues, depending on airplane and test programs, and questions
about who controls the data. We need to understand what the
scenario was and what the war fighter was trying to achieve then
get the data to Raytheon so they can analyze the shot. An important
part of Raytheon's job is to monitor the performance of fielded
missiles and ensure that if any corrections need to be made,
that gets folded back into the development and repair line.
CrossTalk:
What are the most important factors to look at when
beginning a project that indicate which contractor will provide
the most opportunity to succeed?
Stokley: The first thing to look at is past performance. Under
ACT reform we made our past performance evaluations as program
directors mean something. Today we have this neat line that
says, 'If I were going to award a contract in the future, I would,
probably would, probably would not, would not, award again to
this contractor.' The only person allowed to check one and put
their name on it is the program director. It means something
when program directors write it down. We take how we do past
performance evaluations a lot more seriously now so that they
have become more useful.
Second is to get a grip on evaluating the contractor's motives.
'What is the corporations real commitment to this product?' 'Is
this one of many this year, or is this a really important thing to
them?' 'Are they going to go the extra mile?' 'What is their motivation?' During his interview with CrossTalk, Terry
Little, JASSM program manager, also
addressed the following questions.
CrossTalk:
How do you measure contractor performance and stay
alert to foreseeable problems?
Little: We incorporate incremental testing throughout the program,
including ground testing, hardware-in-the-loop testing,
captive testing, and ultimately flight testing. Plus, we are committed
to having an early production representative system. We are
able to look at component deliveries and assess where we are.
One of the dramatic things we did differently is that our program
is front-end loaded in terms of funding and effort. We have
spent 70 percent of our total development budget, and we have
yet to have our first flight test. We focused on maturing the system,
so that when we actually got to flight testing, we would not
be testing a prototype that would still have to undergo manufacturing
development and continued refinement.
It's called "concurrent engineering," which is taught in software
engineering schools and as a program management course.
It's just that nobody ever does it because the pressure on schedule
and money causes everything to be pushed out except those
things directly related to testing. The end result is that a lot of
programs are back-end loaded causing a lot of changes to the system.
This makes for a very long schedule, and a very difficult
transition to production. In our case, factory people using factory
processes, and the same for our supplier parts, produce our very
first development units in the factory.
By the way, we have had absolutely no problems with software.
We are ahead of schedule in a fairly formidable program. It
involves not just the missile's operational flight program, but the
seeker algorithms. With these the seeker finds its own target and
is able to compare what it sees to what it thinks it ought to see.
CrossTalk:
Do you attribute your lack of software problems to
choosing contractors based on their past performance?
Little: We begin with good software requirement definitions up
front based on missile performance requirements. Then we have a
posture here that after defining the initial requirements, there are
no changes until or unless we go through a very bureaucratic
requirements control working group. I'm not talking about user
requirements necessarily, but the kind of program requirements
that come from some ones interpretation of the contract or what
some engineer decides might be a better thing to do or not to do.
We don't change anything unless we know its impact to the program
and we are willing to accept that impact. So we maintain a
very, very stringent control of the requirements.
When legitimate requirement changes arise, such as upgrades
in the software area or additional capabilities, we use a block
change approach. That means we'll do the change and we're willing
to pay for it, but it's not going in the first systems; and it's not
part of our development. There is a very deliberate evolutionary
approach, but we're not trying to do everything at once to satisfy
everyone.
My own experience is that a lot of upgrades and changes come
from people who are not really day-to-day users, but who look at
what might be possible then theorize a use situation. When you
do that without any financial accountability, you end up with
continuing requirements coming to the top. My own view is that
once the system gets out in the field, the real impetus to change,
upgrade, or alter the performance will come from the day-to-day
users.
CrossTalk:
Has part of managing software development been to
get your requirements process under control, whether you've followed
CMMI or not?
Little: Yes, but that doesn't have anything to do with the contractor
per say though. We've gotten it under control because we've
tied a financial accountability to changes. We have a situation in
our business where users establish and change requirements and
for the most part don't assume financial accountability for that.
What we've done with this requirements control working group is
that we've essentially created a situation where people have to
confront the financial and schedule implications of changes. Your
willingness to change when you have to pay for it is always going
to be different than it is when you don't have to pay for it.
What the contractor has from us is performance requirements
for the overall system. He's the one that allocates the software,
hardware, and mission planning. There is absolutely no government
involvement in allocation.
CrossTalk:
Is the government team nonexistent in the software
model?
Little: Yes. We do have government people who are part of interface
control working groups. These groups create an interface
document that consists of the mechanical, electrical, and logical
interface for each aircraft that uses the missile. Once that document
is signed, it is a commitment on both our parts, and the aircrafts parts, to develop to that specified interface.
CrossTalk:
How do you measure contractors' past performance?
Are you looking at the contractor's past work or talking to his
clients?
Little: Initially we ask each of the bidders to provide recent, relevant
performance in several different areas, including cost schedule,
aircraft integration, software development, and production
support. In each area contractors provide three recent contracts
that they think are most related to the job we're bidding. Then we
negotiated with them on their choices because they have a natural
tendency to want to pick and choose ones where they thought
they would have good performance. Then we defined what we
wanted to look at specifically. In software development it was
functionality and scheduling. We asked contractors to assess
these, then we went to their customers for each of these. You
essentially have to develop an algorithm where you can compare
contractor performance not in a general case, but in software performance
that is most analogous to what you're doing. It worked
great for us.
CrossTalk:
Who conducted the analysis, government people?
Little: Yes. But you don't need software government people to do
this. It's a matter of, 'Did you do what you said you would do?'
They were all technical people. The lead of the entire past performance
evaluation was a software person, my chief engineer.
But that was not planned.
CrossTalk:
What parameters in software development were used
to rate past performance?
Little: Essentially functionality, that is, 'Did it do what you said it
was going to do at the start-a promise made a promise kept?
And did you meet the schedule that was laid out?' For comparison
purposes, we also had to incorporate implicit weighting to
balance context. The other thing we did, after we picked the two
contractors based on price and missile performance was to have
each contractor work for a period of time to evaluate production,
price, and performance. 'What did you say you were going to do
here vs. what you actually did?'
CrossTalk:
Do you feel the jury is still out on acquisition reform?
Little: There are a lot of people in the department who want to
say the jury is still out, or even that it's failed. Maybe most people.
I don't believe the jury is out. We have three good examples
of acquisition reform programs. The results are going to continue
to be dramatically different from previous programs. I believe the
primary reason our systems take so long and cost so much has to
do with how the government does business. It is not what the systems
are, but how we have chosen to buy them.
|