Transitioning From SA-CMM to CMMI in the Special Operations Forces Systems Program Office Donald R. Michels, Warner Robins Air Logistics Center Bonnie Bollinger, Consultant
In 1997, the Special Operations Forces Systems Program Office (SOF SPO) at Warner Robins Air Logistics Center,
Robins Air Force Base, Ga., also known as the Special Operations Forces System Program Office Directorate or the LU
Directorate, began a partnership with the Software Engineering Institute (SEI), Carnegie Mellon University, on the use of
SEI's Capability Maturity Model®
(CMM®).
This partnership was started as a result of a desire to implement continuous
process improvement as an institutionalized way of doing business within the directorate. Our initial model was the Software
Acquisition-CMM®.
We continued to use this model until late fall 2000. At that time, the directorate converted to the CMM
IntegrationSM/Systems
Engineering/Software Engineering/Integrated Product and Process Development/Acquisition (hereafter
referred to as CMMI-A). This article explains why the decision was made to change to the CMMI-A, how we became
a pilot organization to test the validity of the model, our training on the model, and what we learned during the course of
conducting a pilot appraisal.
The Special Operations Forces
Systems Program Office (SOF SPO)
at Warner Robins Air Logistics Center
(WR-ALC), Robins Air Force Base, Ga.,
provides combat weapon systems, equipment,
and agile combat support for special
operations and Air Force helicopter
forces. We deliver best value sustainment
and contingency response
through world-class cradle-to-grave
leadership and management.
The SOF SPO has primary responsibility
for systems engineering and
technical services to the SOF Fleets and
Combat Search and Rescue, consisting
of AC-130H/U gunships,
MC-130E/H/P Combat Talon/Shadow aircraft,
MH-53 J/M Pave Low helicopters,
H-1/H-60 helicopters, and CV-22 Osprey
tilt-rotor aircraft.
We recognized that in order to make
improvements, we needed a model on
which to pattern processes. We settled on
the Software Acquisition-Capability
Maturity Model®
(CMM®) (SA-CMM) as a
model that would provide the ability to
assess our processes. The SA-CMM was
structured, contained specific goals,
established levels of competence, and
provided the framework needed to facilitate
improvement. Using the SA-CMM,
the SOF SPO established an improvement
infrastructure, developed a lifecycle
checklist of its directorate's processes,
and started improvement efforts.
The SOF SPO improvement program,
known as the LU Acquisition and
Sustainment Process
Improvement/Reengineering Effort or ASPIRE, made
many improvements during the next
three years. Our successes were of such a
nature that other directorates at Robins
AFB have adopted our process guides for
their own in-house processes. There was,
however, one tiny barrier to complete satisfaction
with the program. It was the use
of the SA-CMM as a model for improvement.
Software development and management
in relationship to acquisition and
sustainment is a very small part of what
SOF SPO does. Since the SA-CMM
referred to primarily software acquisition
and development, it was initially viewed
as a turn-off to the LU work-force. They
wanted something more related to what
they did. In the course of due time, it
even dropped all mention of software
from its process improvement activities.
The work-force simply did not fit the
model, or more accurately, the model did
not fit it. So it continued to search for a
model on which to base its program, but
did not abandon the SA-CMM in the
meantime.
In the fall of 2000, Dr. Thomas
Christian, chief engineer, and Greg
Stanley, deputy director, attended a conference
held in Washington, D.C. During
the conference, SEI presented, in draft
form, a new model: Capability Maturity
Model IntegrationSM/Systems
Engineering/Software Engineering/Integrated
Product and Process
Development/Acquisition (hereafter referred to as
CMMI-A). This model dealt with
processes within an acquisition organization.
Now here was something the SOF
SPO could sink its teeth into. It maintained
the proven structure of earlier
CMM models, but also contained process
areas (PAs) on acquisition. There were, of
course, several questions that needed to
be answered about the model.
When the CMMI-A was
unveiled, not only did the model
address acquisition but it also came
in two versions: staged and continuous.
This was different! The staged
version provides a framework to identify
improvement opportunities and a set
of goals to guide process improvement.
The continuous model groups processes
into categories and designates capability
levels for each process.
In other words, in the staged representation,
the whole organization is
appraised and receives a maturity level
based on an appraisal of all of the PAs
contained in the staged representation. In
the continuous model each PA is
appraised and assigned a capability level.
There is no overall level assigned to the
organization. What is the most significant
factor here? The organization examines
the continuous representation, selects the
PAs that either apply to the organization
or are PAs the organization wants to
improve upon, and uses only the selected
PAs during appraisals.
So here we have the old SA-CMM
model and the new CMMI-A model with
two different representations -- staged
and continuous. What do we do?
Dr. Christian and Stanley returned to
Robins to brief me and my staff on the
new model. We discussed at length our
partnership with SEI, the advantages and
disadvantages of the SA-CMM and the
CMMI-A, and the LU workforce's desire
to find a model more suited to what we
do. Many questions and answers were
posed: "Has it been tested?" "No;" "How
do we know it will work?" "We don't;"
and "Has anyone been appraised using
the model?" "No."
In the end, we decided that even with
these negative responses, the CMMI-A
with continuous representation was
worth our time and effort as a model for
process improvement. Finally, we had a
model that fit us; we did not have to try
to fit the model. Transition to CMMI-A
During their Washington, D.C. trip, Dr.
Christian and Stanley discussed the new
model with Dr. Jack Ferguson, deputy
Acquisition Resources and Analysis director
for Software Intensive Systems,
Office of the Secretary of Defense,
regarding adopting and implementing the
model. They pointed out that it had not
been tested or implemented anywhere
else. Dr. Ferguson asked them to consider
using LU as a pilot appraisal organization
to test the new model. He would
secure the necessary funding to conduct
the appraisal. We agreed, and dates were
established. We were now on the road to
the CMMI-A implementation in the SOF
SPO.
We developed three immediate objectives
concerning implementing the
CMMI-A in LU. First, we wanted training
on the new model. Second, we needed
to determine the specific PAs on
which to be appraised. Third, we wanted
a balanced team of appraisers.
The first objective, training, was easy
enough. We contracted with SEI to provide
training for 30 LU personnel in
February 2001. Participating in the training
were most of the personnel selected
to be on the appraisal team. Training covered
the two model representations and
the process areas within each; however,
the three-day session was only able to
present the basics of the model. Training
feedback primarily concerned the depth
of training they were able to present in
three days. While the instructors were
very professional and knowledgeable, it
was very difficult to come to a level of
familiarization with the model in only
three days. All agreed that training needed
to be longer and more in-depth.
We devoted a lot of effort to ensuring
the composition of the appraisal team
was as balanced as we could make it. Our
considerations in putting the appraisal
team together centered on three central
thoughts. First, we needed people experienced
in conducting appraisals and using
previous CMM models. Second, we wanted
to make sure the team consisted of
people experienced in acquisition and
sustainment activities. The latter proved
invaluable in interpreting the wording of
the model into LU activities. Finally, we
needed to make sure we had a team composed
of personnel from both external
and internal sources.
We were able to achieve all three of
these objectives. The team was composed
of five LU personnel, three other WRALC
personnel who had appraisal experience,
one representative from SEI, and
an experienced appraiser from the
Software Technology Support Center,
Hill Air Force Base, Utah. We felt this
personnel combination provided the
expertise and objectivity needed to conduct
a thorough appraisal. After establishing
the team, our lead appraiser began
a series of training sessions designed to
teach our functional experts how to conduct
an appraisal.
In examining the CMMI-A with continuous
representation, we needed to
decide which PAs to appraise. In order to
accomplish our objectives and the need
to "test" the model, we settled on 17 different
PAs, see Table 1. These included all
the PAs we used in our initial appraisal
back in 1997 and added several new PAs.
The groundwork for conducting the
appraisal was now completed.
 Table 1: Process Areas
Conducting the Appraisal
Conducting the appraisal required a great
deal of time and effort. The preliminary
step was to survey the work-force. The
team then gathered all pertinent data and
documentation from the "projects" being
appraised. The team then briefed us on
how they would conduct the appraisal
and developed a series of questions to
use in the personnel interviews.
Interviews were conducted over a series
of days and provided the bulk of information
used in determining our capability
levels. Their final step was to correlate
all the available information and assign a
capability rating to each PA.
The team interviewed 47 people,
reviewed more than 112 documents, and
worked 130 hours during two weeks. The
team examined every detail of the selected
process areas. Using a team decision
process, the results for LU were extremely
gratifying. Sixteen of the 17 PAs
received a capability rating of Level 2 "A
Managed Process." One PA,
Organizational Process Focus, was rated
Level 3 "Defined Process." This was
quite a remarkable achievement for an
organization that four years earlier had no
documented processes at all and had not
used the model to develop its technical
activities of systems engineering and configuration
management.
Especially remarkable was the Level 2
rating given three Integrated Product and
Process Development (IPPD) areas:
Integrated Teaming, Integrated Project
Planning, and Integrated Supplier
Management. We had not been able to
plan and implement procedures and
processes for the IPPDs due to the fact
they were not fully defined by SEI until
shortly before the appraisal. These ratings
demonstrated we had intuitively recognized
and were already in conformance
with the standards established for the
IPPDs at the time they were being developed
by SEI.
Based on these results, we developed
an action plan to address weaknesses in
our processes. Our primary focus will be
to establish a measurement and analysis
program in order to move us to the next
capability level for our selected PAs. Our
commitment to process improvement has
only been strengthened by our conversion
to the CMMI-A. Lessons Learned
Every decision we make, regardless of
the subject, teaches us something. It
either reinforces our thought process as
being correct, or it shows us where we
didn't think things through. Converting
to the CMMI-A was the correct decision,
but we did learn a few things along the
way: some about our program, some
about the model, and some about the
appraisal process.
We learned that training on the model
should be spread out and more in-depth.
Our personnel on the appraisal team and
the work-force could have used additional
training, which would have eased our
transition. Feedback from members of
the appraisal team leads us to believe had
they had a better understanding of the
model, we would have received higher
capability ratings in several more PAs.
We learned that reviewing organizational
documentation should begin as
soon as possible. We waited until the last
minute to send out our survey. It was
quite extensive and required time to
respond. Unfortunately, our delay caused
recipients to feel pressured to respond
quickly, so most ignored it. It also gave us
very little time to analyze the results.
We also realized the scope of the
appraisal was much too great for the
amount of time and number of interviews
needed to cover the PAs. The team
reviewed more than 112 documents. With
all the other things the team needed to
accomplish, this was too much to review
at a moment's notice. We found examination
of 17 different PAs too much to
accomplish within a two-week period. We
recommend you restrict yourselves to the
more important PAs (probably around
10) or make a decision to appraise some
now, some later. Careful selection of the
PAs would result in a more reasonable
effort.
Lastly, while the appraisal methodology
calls for the appraisers to construct
questions that solicit data about your
processes without being direct, our interviewees
found this to be both frustrating
and confusing. If you decide to follow
the current interview methodology, you
will need to brief the interviewees that
you intend to ask general questions and
will be looking for specifics based on
their answers. Constructing questions
concerning "how, why, and where" may
be a more efficient method. Looking Forward
The SOF SPO has a long and productive
relationship with process improvement.
From senior leadership down to individual
members of our Process Action
Teams, we have developed an appreciation
of making things better. Our association
with the CMM has only enhanced
this appreciation. The CMMI-A is our
guide to the future. We are convinced our
involvement with the CMMI-A is a key
factor in why we have developed a "passion
for excellence."
About the Authors
 Donald R. Michels,
GS-15, is the director
of Special Operations
Forces Systems Program
Office at Warner Robins
Air Logistics Center,
Robins Air Force Base, Ga. He is the
U.S. Air Force's single manager for
fleet management of Air Force
Special Operations Command fixed wing
aircraft and all U.S. Air Force
helicopters. He directs more than
420 personnel at Robins Air Force
Base, Wright-Patterson Air Force
Base, Ohio, and other operating locations.
He also directs oversight of
more than 20 contractor support
agencies. Michels has a bachelor's
degree in management from
Metropolitan State College, Denver,
Co., a master's degree in logistics systems
from Georgia College and State
University, Milledgeville, Ga., and is a
graduate of the Air War College,
Maxwell AFB, Ala. He is also a graduate
of the Defense Systems
Management College's Program
Management Course and holds
Acquisition Professional Development
Program Level 3 Certificates in both
Program Management and Acquisition
Logistics.
Bonnie Bollinger is a former GS-12,
software engineer, and was assigned to
the Avionics Directorate at Robins Air
Force Base, Ga., prior to her retirement
from federal service in 2001.
The Software Engineering Institute,
Carnegie Mellon College, Pittsburgh,
Penn., has certified her as a lead assessor.
Bollinger is currently a private
consultant to SEI and government
agencies.