A Project Risk Metric Robert W. Ferguson, Software Engineering Institute
A risk metric is proposed that is normalized across projects. The purpose of the metric is to provide management visibility
into project uncertainty. This works best in an organization that manages multiple projects. The proposed metric can be
applied early and throughout the project. It has been useful for identifying or canceling projects in trouble. It has also been
useful for identifying projects that do not yet have a satisfactory risk plan.
The Standish Group published its original
"Chaos Report" [1] in 1994
declaring that American companies spent
$81 billion on cancelled projects.
Additional Standish Group data in Figure 1 shows that the situation has not
improved as much as one would hope.
 Figure 1: Standish Group Project Results
Even projects that are not cancelled
may deliver such reduced functionality
that most people would not count them as
successful projects. Often there has been
early evidence that the project was headed
for disaster. The project manager may
even have issued warnings to senior management
or sponsors about the problems.
There simply seemed to be no way to pull
the plug until the project was already over
budget, late, and at the point where the
customer was ready to give up or worse.
The problem may be a failure to examine
the risks of the project from a systemic
view. When risks are faced one
problem at a time, the management team
may convince themselves that every problem
can be addressed, or that each problem
has a low probability of occurrence.
However, the collected problems may still
be too much to manage. By its very nature,
risk is statistical. It is possible to examine
the collection of risks and make some
projections about the project's likely success
or failure. The result can even suggest
that certain projects should be cancelled
very early. Such projects can be rescoped
and rebudgeted in a way that improves the
focus and likelihood of success.
Risk Management Process
The Project Management Body of
Knowledge (PMBOK) [2] includes a
chapter on risk management. It describes
the process steps as follows:
- Risk Planning.
- Risk Identification.
- Qualitative Risk Analysis.
- Quantitative Risk Analysis.
- Risk Response Planning.
- Risk Monitoring and Control.
The metric proposed in this article fits
the Qualitative Risk Analysis stage so it
can be used as early as possible throughout
the project duration. Rough estimates
are available at this step, and are sufficient
for an assessment of the overall project
risk. However, the rough estimates will
not suffice for risk items requiring real
risk-response strategies such as mitigation
and avoidance plans where more detailed
work is needed.
In this metric, the distinction between
steps three and four of the process model
is important. The metric supports the
viewpoint of senior management who
wants to determine which of several projects
has significant uncertainty. The project
itself must deal with specific risks and
quantitative analysis. As such, a risk manager
on a large project will not find this
metric as useful. He or she must have
much more specific information.
History and Metric Definition
Risk is both old and new. The written history
of risk begins in 1491 with the
"Pacioli Puzzle," which arises from gambling
when the game is stopped before
completion [3]. The problem was solved
by Pascal and Fermat in 1654 and so
began the use of risk in forecasting. Today,
risk is the core concept in insurance and
has become a major focus in project management.
A standard definition of risk is an
uncertain event that would cause an
uncertain impact on project schedule,
cost, or quality. Both the event and the
impact have the element of uncertainty.
The definition from probability theory is a
bit more restrictive but it provides us with
the metric:
R = P x V
The metric value of risk (R) is the
product of the probability (P) of the event
with the most likely value (V) of the outcome.
If the risks are independent, we can
add these estimates together for a combined
estimate. So overall project risk is
the sum of the separate risks.
Total Risk = Sum of all (P x V)
The Total Risk value and trends of
Total Risk provide a picture of the project,
making it easy for people to see some good
and bad project patterns without delving
into the statistical theory. The assumption
about independence is necessary for the
theory. However, in practice, risk management
experts are aware that risks are not
always independent. The metric is based
on the theory derived from gambling
where the assumption holds true.
Getting the Probability
There have been a few sociological studies
showing the range of errors people
demonstrate in estimating risk. Choosing
an appropriate range helps when no historical
data is available. Table 1 and its
heuristics have been useful in avoiding the
problems of underestimating and overestimating
risk. Remember, most project managers
see only three to five projects in their
career at any one company so they work
from a very restricted sample. They need
heuristics for estimates.
 Table 1: Risk Event Probability Estimates
(Click on image above to show full-size version in pop-up window.)
Five levels of probability seem to work
well. Colleagues have not had a problem
assigning an event to one of the recommended
levels, so the suggested ranges
provide good separation.
Analyzing the Impact
The impact of a project risk-event needs
to be similarly divided into a few classifications
and assigned a numeric value to manage
risk. Making the numbers match conceptually
when one risk affects schedule,
another cost, and another quality or scope
can be a bit of a stretch so a method is
required to normalize the numbers.
A quick simplifying assumption works
for the qualitative analysis stage: assign a
single impact type. Choose from one of
the following three image types: schedule,
cost, or customers (sales). It is true that a
risk event may affect more than one of
these, however, coming up with a value for
all the possible effects is challenging and
probably not a worthwhile exercise until
quantitative analysis. Narrowing the discussion
of a risk event to a single type
impact also focuses attention on the most
useful response plans. This approach helps
to avoid the problem of overthinking the
impact of a risk. Here is an example of the
kind of thinking to avoid at this early
stage.
Some employees are due for sabbatical
leaves of two months. One
may take that sabbatical during the
project. You propose that turnover
is a risk for the team. If this risk
event occurs, it may cost some
additional schedule time and additional
resource cost to hire and
train staff. If you lose schedule
time, you may also lose some sales.
What is the appropriate impact for
this event — schedule, cost, or sales?
Experienced risk managers will understand
that additional impacts will have to
be considered when developing the riskresponse
plans.
Normalizing Risk Impact
The next challenge is normalizing the various
impacts to arrive at a single numeric
value for schedule, cost, and sales. Capers
Jones reported that in 1996 "the typical
project is 100 percent over budget when it
is cancelled" [4]. This suggests that a useful
normalizing factor is to set maximum
risk impact at project cancellation. That
impact value should be cost or schedule
overrun of 100 percent, or when there is
no customer or no potential first-year sale.
Of course, no project will be allowed
to overrun to such an extent without
senior management intervention, but that
is precisely the point. Senior management
should intervene when the uncertainty
suggests the project is in trouble. Since the
metric is applied at qualitative analysis,
there is time to recover.
A Second Aside
Why would we develop a product
without customers? No one plans a
project for a non-existent market,
but the market can disappear or be
misjudged. It happens all the time.
Some well-known examples are the
Newton tablet computer, the
Iridium satellite telephone, and
New Coke. Everyone also has an
example of the pet project that was
developed but was never used.
Many organizations are surprised
to learn that it is possible to cancel
a project when sales or number of
customers are factored into the risk
management effort.
Using the possibility of cancellation as
the highest risk impact, assign a value of
five to cancellation. Five levels of risk
should be enough. Creating the other levels
again requires a bit of psychology. The
PMBOK states an order of magnitude
estimate is plus or minus (+/-) 35 percent of
the base estimate. Using a range of 1 +/-
0.35 is a range of 0.65 to 1.35. The ratio of
these two numbers is 1.35/0.65 = 2.08,
approximately a factor of two.
Thus to have a range that clearly separates
the estimates, we must use a larger
value. Using +/-50 percent yields a ratio of
1.5/0.5, which equals a factor of three.
Experience suggests the psychology
works, and people are comfortable with
the results. Therefore, assign five to cancellation
and divide the cancellation level by
three successively to arrive at the other values.
The following example points the way.
Consider a project that is scheduled for
18 months with a projected cost of $30
million and projected first-year sales of
$27 million. This would be a project of
about 100 people with about $5 million in
external expenses. A risk event with an
impact level of five would cause the following:
- Overrun by 18 months.
- Overspend by $30 million.
- Achieve no first-year revenue.
A risk event with an impact level of four
(divide by three) would cause the following:
- Overrun by six months.
- Overspend by $10 million.
- Lose $9 million in sales (achieves $18
million).
A risk event with an impact level of three
would cause the following:
- Overrun by two months.
- Overspend by $3.3 million.
- Lose $3 million in sales.
A risk event with an impact level of two
would cause the following:
- Overrun by three weeks.
- Overspend by $1.1 million.
- Lose $1 million in sales (one customer).
A risk event with an impact level of one
would cause the following:
- Overrun by one week.
- Overspend by $300,000.
- Lose $300,000 in sales (customer
delays six months).
A useful interpretation is to say that the
project manager can manage one or two
risk events of impact level one within the
project contingency and without unusual
reporting. It would be necessary to generate
a special report for any occurrence of
impact level two. Any risk event at impact
levels three or higher will require senior
management's involvement to determine
the response.
There is one more step in calculating
the final impact. The numbers one
through five were calculated by successive
division by three. The final value has to put
that back into a geometric scale.
Impact = 3^(level-1)
So a risk event with an impact level of five
has an impact value of 3x3x3x3=81, as
shown in Table 2.
 Table 2: Impact Value Adjustment
The factor three is not arbitrary but is
derived from the observation that orderof-
magnitude estimates use a factor of two
for the error range.
There is a temptation to turn the numbers
back into dollars. This is a lot of work
as revenue dollars are not the same as cost
dollars or schedule days. The extra work
makes sense for the top risks but not in
general. Using the impact number instead
of a dollar value also normalizes the risk
metric across projects.
Risk Calculation
The final risk calculation follows the original
equation:
Risk = Probability x Impact Value
The highest risk is 95% x 81 = 76.95
The lowest is 5% x 1 = 0.05
Normal usage is the sum of the highest
20 project risks. It seems that 20 risks at a
time is a sufficient number to track for all
but some mega-projects (over three years
and more than 500 people). Barry Boehm,
TRW professor of software engineering at
the University of Southern California and
author of the COCOMO estimating
model, has suggested that projects manage
the top 10 risks. There are two reasons this
metric recommends watching the top 20.
The first is that 20 risks x 5% = 100%. That
is the recommended cancellation level so it
makes for a convenient metric. The second
reason is to make certain the project team
investigates more than the first 10 risks to
be certain that it manages the top 10.
Project Risk Score = Sum (highest 20 project risks)
Implications
The Project Risk Score should be charted
so senior management can see scale and
trends. Since there is a threshold (threatened
cancellation) implicit in a risk with
impact level five, that threshold should also
appear on the chart. An impact level equal
to five translates into an impact value of
81. Figure 2 is a sample chart from an actual
project.
 Figure 2: Sample Project Risk Score
(Click on image above to show full-size version in pop-up window.)
There are many implications in the
chart and its use. The threshold is a powerful
concept. Senior management will focus
a lot of attention on a project that is above
the threshold. The fact is, projects with risk
higher than the threshold simply will be
late, over cost, or fail to meet project quality
goals. Some projects have risk levels that
are astronomically high. It is theoretically
possible to see a value of 1,539 with 20
risks that are very likely to occur and have
an impact rating of five. Of course, such a
project should be cancelled and restarted. I
have actually seen only one project risk
value over 400. That project had to make
major changes to deliver even a subset of
the desired functionality. If the threshold
concept had been introduced at the start of
that project, it would never have gotten
into so many problems.
A somewhat opposite situation also can
occur when a project shows particularly low
risk. The project manager or senior management
may have a sense that a project is
at significant risk, but the metric does not
show it. Use that low number as a signal
that a risk collection effort is needed. The
project manager must gather a wider audience
and run a facilitated session to identify
those other risks. Make sure to include
stakeholders from other locations and
groups outside the development team.
Develop the organization taxonomy for
risks like the one in the "Continuous Risk
Management Guidebook" [5] from the
Software Engineering Institute to make the
data collection more complete and rigorous.
A normal response when the project
risk is high is to manage that risk down.
This can happen several ways:
- The time for the risk event may pass
without incurring the problem.
- The team may adopt an avoidance plan
so that the event cannot occur.
- The team may adopt a mitigation plan
to reduce the impact.
- The team may transfer the risk to
another organization.
- The event may occur and the project
eats the contingency.
The last four responses cause the project
to incur a specific cost that should
appear in the project planning and reporting.
Each of the responses requires the
project manager to make some update to
the risk database.
Finally, product managers (not project
managers) should be hesitant to select a
project of very low risk. If the risk is so
low, why not address a more aggressive
product plan? Risk avoidance is not generally
a winning strategy in the marketplace.
The point is to manage risk to appropriate
levels for the organization, product, and
project. Risk management is a systemic
study and not a technological one.
Implementation
There are several challenges in adopting
the project risk metric. The following is a
list of the top challenges:
- A database for collecting and managing
risks. There are a number of
products that will do the job. Implementing
one will require the addition
of project and sub-project identification
and organizational process support.
This work cannot be institutionalized
without an automated system.
- A process model. The basic framework
is available in the PMBOK, the
Continuous Risk Management Guidebook,
or the Institute of Electrical
and Electronic Engineers standard for
risk management [6]. The process
model has to be extended to cover a
risk taxonomy that is appropriate to
the organization.
- Automated reporting. Chances of
success are better if the project risk
chart is automated and is required as a
part of the regular project management
review. The risk metric should be
checked at least monthly.
- Training. Training is a big effort.
Training project managers to do risk
management takes days, not hours.
Writing good risk scenarios requires at
least eight hours of training and much
practice. Learning the organization
taxonomy of risk takes time.
Evaluating impacts probably takes
three hours of training. Directors and
senior managers also need at least
three hours of training. Do not
attempt to implement a project risk
metric without decent training on risk
management.
Summary
Many seasoned project managers say that
advanced project management is mostly risk
management. This metric makes that statement
visible and concrete to a much larger
audience. It provides fast visibility and has a
high emotional impact on managers.
The project risk metric, however, has
been tested in only one location and on
only a dozen projects. The simplifying
assumptions made in order to develop and
use the metric make it suspect for use by
risk practitioners who must perform
detailed quantitative analyses and develop
risk mitigation and avoidance plans.
It does provide a comparison between
projects that is useful to senior management.
If senior management is presented
with one risk at a time, they are likely to
develop a confidence that they can deal
with each risk as it comes. Dealing with
each risk separately and successfully may
convince them that the project cannot really
be in trouble. Management may then
come to believe that the project team is
whining about problems instead of dealing
with problems, and real risks may not be
addressed in a timely fashion. Presenting
senior management with a picture of the
total project risk will encourage them to
take appropriate systemic actions when
these are necessary. Product managers on
projects with high risk will need additional
justification and resources to add scope.
The development team may have an easier
time getting training or adding consultants
when needed.
The key is presenting senior management
with better visibility into the project
so that project change-management becomes
faster and easier, and finally, so that
product delivery becomes predictable.
References
- The Standish Group International, Inc.
CHAOS Chronicles Ver. III. West
Yarmouth, MA: The Standish Group,
2003 www.standishgroup.com/chaos/toc.php.
- Project Management Institute. A Guide
to the Project Management Body of
Knowledge (PMBOK Guide). Newton
Square, PA: Project Management Institute,
1996 www.pmibookstore.org/productdetail.asp?productid= 4106.
- Bernstein, Peter L. Against the Gods:
The Remarkable Story of Risk. Hoboken,
NJ: John Wiley and Sons, 31 Aug.
1998 www.wiley.com/WileyCDA/WileyTitle/productCd-0471295639.html.
- Jones, Capers. Patterns of Software
Failure and Success. Boston, MA:
International Thompson Computer
Press, 1996.
- Durofee, Audrey J., et al. Continuous
Risk Management Guidebook. Pittsburgh,
PA: Software Engineering
Institute, 1996 www.sei.cmu.edu/publications/books/other-books/crmguidebk.html.
- Institute of Electrical and Electronic
Engineers. "Software Engineering:
Software Life-Cycle Processes, Risk
Management." Proposed Standard.
New York: IEEE, 2004 http://standards.ieee.org/announcements/pr_p1540.html.
About the Author
 Robert W. Ferguson is
a member of the
Technical Staff at the
Software Engineering
Institute. He has more
than 30 years of software
development and management
experience in several industries.
Ferguson is a member of the
Computer Society of the Institute of
Electrical and Electronic Engineers
and the Project Management Institute.
He has been active in the software
process improvement community for
several years and is past chairman of
the Chicago Software Process
Improvement Network.